The World Bank logo on its headquarters building
An additional Financing Agreement was signed yesterday between the Government of Bangladesh and the International Development Association (IDA) of the World Bank Group for an amount of $95.00 million to implement "the Resilient Urban and Territorial Development Project (RUTDP)".
The project has been under implementation since 2025 and is scheduled to continue until June 2030. The implementation period for the additional financing is until 30 June 2030.
Md. Shahriar Kader Siddiky, Secretary, Economic Relations Division, Ministry of Finance and Jean Pesme, Division Director of the World Bank for Bangladesh and Bhutan, signed the Financing Agreement on their respective sides, said an ERD press release today.
The project is being implemented by the Local Government Engineering Department (LGED) under the Local Government Division (LGD), Ministry of Local Government, Rural Development and Cooperatives.
The project aims to (i) enhance delivery of basic urban services, including Operation and Maintenance, (ii) improve municipal governance, fiduciary management, and own-source revenue generation, and (iii) strengthen the institutional capacity of Pourashavas and City Corporations in planning, procurement and financial management, implementation, operation and maintenance.
The total allocation for the original project was $400.00 million, out of which US$ 95.00 million was repurposed for the Contingency Emergency Response Component (CERP).
Hence, to ensure the continuation and completion of the project as per the Development Project Proposal (DPP), an additional $ 95.00 million financing has been secured.
Out of $ 95.00 million, $ 92.00 million equivalent SDR 67,300,000 (sixty seven million three hundred thousand Special Drawing Rights) will be provided from the Scale-up Window-Shorter Maturity Loan of IDA.
The repayment period of the loan is 12 years, including a grace period of 6 years. No service charge, commitment fee, or interest will be paid on the amount withdrawn from this loan.
The remaining $ 3.00 million equivalent SDR 2,200,000 (two million two hundred thousand Special Drawing Rights) is being taken from World Bank's Performance- Based Allocation. The interest charge is 1.5%. This loan amount is repayable in 25 years with 05 years grace period.
The World Bank is the largest multilateral development partner of Bangladesh. This financing reflects the deep cooperation between Bangladesh and the World Bank. Currently, the World Bank financing covers a wide range of sectors, including economic and social development, institutional reforms, infrastructure development, and energy sector advancement.